The final west-side pedestal for planned period lighting was placed Wednesday on Main Street between Central Avenue and First Street SW.

All base repair and subgrade work was is complete in the block south of Central Avenue and crews have started filling to final grade for placement of concrete.

Work began Thursday to remove concrete and rebuild sub-grade on First Street SW to the alley.

Additionally, work crews began setting final elevation base on Main Street from Central Avenue to First Street South.

Bids were opened at 10 a.m. Thursday for concrete work. The placing of forms is expected to start Monday.

The project remains on schedule.